What is defined as the installation of all plumbing system parts that can be completed before the installation of fixtures, including drainage piping, water supply piping, vent piping, and fixture supports?

  1. Water Distribution Pipe

  2. Roughing-in

  3. Barometric Loop

  4. Developed Length

The correct answer is: Roughing-in

The term that describes the installation of all plumbing system components that can be completed prior to the installation of fixtures is "roughing-in." This process includes laying out and connecting drainage piping, water supply piping, vent piping, and fixture supports, ensuring that all the necessary infrastructure is in place for a smooth installation of the actual fixtures later on. Proper roughing-in is essential for the functionality and efficiency of the plumbing system, as it lays the groundwork for everything that follows. Other options do not encompass this broader aspect of plumbing installation. For instance, the water distribution pipe refers specifically to the pipes that deliver water to various fixtures, while a barometric loop is a specific plumbing configuration used to equalize pressure in certain systems. Developed length is a term used to describe the total length of a piping run, including all its angles and bends, rather than the installation process itself. Thus, roughing-in is the most accurate description of the initial phase of plumbing installation mentioned in the question.